Whittlesey Road traffic light crossing improvement

Highway improvements – Whittlesey Road traffic light crossing improvement

No photo description available.

Just a heads up, dates subject to confirmation.

Whittlesey Road traffic light crossing improvement is an upgrade to the existing traffic light crossing point. There will be new traffic lights and crossings signals installed with new tactile paving and asphalt.

Works will start on 03/02/20 and run until 28/02/20 and will be carried out under 2 way lights from 09:30 – 15:30 hrs.

Carriageway resurfacing will be carried out under a road closure also from 09:30 – 15:30 hrs. Surfacing works is likely to take 2 days.

Letters to residents and advance warning signage to follow and dates will be confirmed.