The latest roadworks programme received from Skanska is as follows:

Surfacing works will be carried out on 7th and 8th October on Whittlesey Road utilising the current closure and not at the end of the programme, as originally planned.

On 9th October, the Phase 1 works will conclude and the traffic management will be switched. Whittlesey Road will re-open and South Street/Fletton High Street will close.

Phase 2 will then run from 9th October to the end of the works on 25th October, a reduction of nearly three weeks.

Carriageway surfacing between the roundabouts will take place on 21st/22nd October under a full closure of the junction (08:00-16:00). This will coincide with the school half term holiday.