Whittlesey Road/Fletton High Street/South Street Roadworks – Diversion Routes

Whittlesey Road/Fletton High Street/South Street Roadworks – Latest

After our request, the diversion routes for each phase of the works have been released and are shown below.

Scheduled dates for the works are as follows:

No photo description available.

Phase 1 commences on 12 August for 4-6 weeks

No photo description available.

Phase 2 -3rd week of September

No photo description available.

Phase 3 – end of September/early October.

No photo description available.

Phase 3 Close Up – end of September/early October.

All works will be day time works. The Phase 3 surfacing works will be undertaken between 09:30hrs and 15:30hrs.

The traffic management will be monitored during the works. The contractors intend to undertake the majority of the works in Phase 1, in order to limit the impact on traffic management.

PCC are in discussions with the bus company regarding the best routes around the proposed works.